Please ensure Javascript is enabled for purposes of website accessibility
Notice 08-27-2025 : Effective Immediately the Hillside Road Bridge is Closed. We will notify here when reopened.

Town of Linn Road Paving to Start Next Week

Weather pending, here is the Town’s tentative road replacement schedule:
 
May 5         Pave wedge on Stateline Rd (Knickerbocker to Highfield)
                   Mill on Laural St. and possibly Maple
May 6        Pave surface on Stateline Rd. (Knickerbocker to Highfield)
                  Finish milling on Maple and/or mill Zenda Rd. (County Highway B to Mohawk Road)
May 7        Finish Stateline Rd. paving (Knickerbocker to Highfield)
                  Pave surface on Laurel St.
May 8       Pave surface on Maple Ln.
                   Pave on Zenda Rd (County Highway B to Mohawk Rd)
                   Pulerize and grade Leedle Ave.
May 9      Finish Paving on Zenda Rd (County Highway B to Mohawk Rd)
                  Possible lower on Leedle
                  Shoulder on Stateline Rd. (Knickerbocker to Highfield)
Additional road shouldering and striping will continue shortly thereafter. Questions? Please contact Highway Superintdendent Matt Wittum at 262-275-6300 ext. 17.